Fifty-seven projects on the state's list. Seven have money and a permit on the record.

What the public record establishes for every data center on Pennsylvania DEP's tracker.

Version 1.0 · Published 2026-09-13 · Grades as of 2026-08-22 · Sources pulled 2026-08-19/20

This report is a snapshot, not the current state of the list

Every grade below is as of 2026-08-22 and has not been re-reviewed since. The report covers the 57 projects on DEP's tracker on 2026-08-19; the tracker has kept growing — 71 projects as of 2026-09-29 — and projects added after 2026-08-19 are not graded here. Four local decision dates have passed without re-review (details below). For the current list of projects and permits, use the Pennsylvania map.

Summary

Pennsylvania DEP's Data Center Permit Tracker listed 57 projects on 2026-08-19. We graded every one of them against three kinds of public evidence: a DEP filing, a local approval, and financing or a named end user. Seven have all three on the record. Twenty-six have one or two. Twenty-four have a DEP row, a press mention, or a land position, and nothing else.

57
projects on DEP's tracker
as of 2026-08-19
7
Established
filing + local approval + money or end user
26
Partial
one or two of the three legs
24
Announced only
a row, a mention, or land; nothing else

Table A (20 projects with a DEP permit application): 7 Established · 13 Partial · 0 Announced only. Table B (37 projects DEP lists with no application): 0 Established · 13 Partial · 24 Announced only.

Since this was graded

How to read a grade

A grade counts which of three kinds of public evidence exist for a project on the date shown:

  1. A DEP filing. At least one permit application on DEP's tracker, applied or complete.
  2. A local approval. A municipal zoning, conditional-use, or land-development approval on the record.
  3. Money or a named end user. Committed financing, drawn debt, a power purchase agreement, a signed capital transaction, or a publicly named tenant or operator-owner.
Established
A DEP filing, a local approval, and financing or a named end user — all three on the record.
Partial
One or two of the three legs; the missing leg is named in the reason.
Announced only
A DEP row, a press mention, or a land position, and nothing else in the record.
A grade is not a forecast. It states which of three kinds of public evidence exist for this project on the date shown. Grades change when the record changes, and anyone can dispute one.

In our working files these grades are called Real, Watch, and Zombie; the criteria are identical. Every row below carries its grade, a one-line reason, its source tags, the as-of date, and a Dispute this grade link. Blank or "not published" means no public document states it.

Revisions

Grades were first drafted on 2026-08-19 from the tracker and press. On 2026-08-20 every Table A row was re-verified against DEP's permit-level data and named sources (rows touched are marked †). On 2026-08-22 the editor reviewed the verification findings and changed five grades:

The editor also confirmed B1 Homer City as Partial and set the rule it illustrates: we grade the row, not the campus. An energy campus's reality does not transfer to an unfiled data-center row. Outcomes of disputes are posted here.

The reading

Seven of the 57 projects on the state's list have money and a permit on the record. Of the 57 on DEP's Data Center Permit Tracker [D], the grading pass finds 7 Established, 26 Partial, and 24 Announced only — consistent with the Executive Order's own finding that "most proposals are speculative, with no identified end user" [EO].

The seven Established projects share one shape: money and machine already on site — a power purchase agreement, a signed capital transaction, drawn project debt, unanimous final approvals, or active construction. They are A1 Salem Township (AWS) · A2 Falls Township (AWS) · A3 216 Greenfield Road (Chirisa / CoreWeave) · A4 Keystone Connect (TECfusions) · A6 Project Phoenix (Aligned) · A8 QTS Salem · A19 Sharon (Keel) [D][T]. Nothing in Table B — the 37 DEP-listed projects with no permit application filed — is Established; that half of the list is 13 Partial and 24 Announced only [D].

What the new regime does to the unfiled rows is the other half of the reading. Executive Order 2026-05 applies to applications submitted after 2026-08-18 [EO]; every Table A application predates that cutoff (the latest was submitted 2026-08-07 [DP]), so the order reaches each of those projects exactly where its unfiled phases live [COA]. For Table B the exposure is total: with nothing filed before the cutoff, every future permit application lands inside the order, and any project over 25 MW that wants the coordinated-review lane signs the full template Consent Order and Agreement with no Addendum A relief, because the existing-permittee gate requires a pre-order application [COA]. The agreement trades that one thing — staying in the coordinated-review lane — for perpetual, campus-wide obligations that reach tenants, carry per-megawatt-per-day penalties, and waive nearly all appeal rights [COA].

EO 2026-05 and the Consent Order in one page

The order. Executive Order 2026-05 was signed 2026-08-18 and took effect immediately. It covers data centers over 25 MW through DEP template Consent Orders and applies to applications submitted after 2026-08-18. Paragraph 1e removed all data centers from the Fast Track program (nine projects had been flagged) [SP][HN]. Paragraph 2a bans agency non-disclosure agreements. Paragraph 2b mandates a state-published public map of all proposed projects — the DEP tracker itself [D-APP]. It sits on top of the PA PUC large-load model tariff (final order 2026-05-13, for loads of 50 MW and up) [PUC].

What signing the template Consent Order and Agreement obligates [COA]:

Table A — projects with a DEP permit application (20)

A grade is not a forecast. It states which of three kinds of public evidence exist for this project on the date shown. Grades change when the record changes, and anyone can dispute one.

DEP Permits=YES rows. MW is the announced or filed capacity; DEP's tracker carries no capacity field. "COA-likely" is our read of whether the project has unfiled phases that would put it inside the Consent Order regime. The tables scroll sideways on small screens.

#ProjectCountyMWDEP stageLocal approvalsEnd userFinancing signalCOA-likelyGradeReasonSourcesAs of
A1Salem Township DCAmazon Web Services; power: Talen EnergyLuzerne1,920 (phased from 840)DEP review complete; formerly Fast Trackyes — overlay rezoning approved 5/2024; under constructionyes — AWS$18B AWS–Talen nuclear PPA to 2042; part of AWS's $20B PA programno for phase 1; yes for later phasesEstablishedPermits complete, local approvals, named end user, and capital all on the record; under construction[D][T][SP]as of 2026-08-22Dispute this grade
A2Falls Township DCAmazon Web Services; Keystone Trade CenterBucksnot publishedDEP review complete; formerly Fast Trackyes — zoned industrial, land secured; first building under construction (township began a 180-day zoning rewrite 7/2026; project treated as grandfathered)yes — AWSPart of AWS's $20B PA programno for phase 1; yes for later phasesEstablishedPermits complete, zoning, and named end user on the record[D][T][SP] †as of 2026-08-22Dispute this grade
A3216 Greenfield RoadChirisa Technology Parks / CoreWeave; Machine Investment Group, Blue OwlLancaster~300 planned (Phase 1 ~100)DEP review completeyes — Phase 1 under construction inside existing buildings; Phase 2 new-build awaits city land-development approvalyes — CoreWeave~$6B CoreWeave commitment; Blue Owl / Machine Investment Group capitalno for phase 1; yes for the expansionEstablishedPermits complete, Phase 1 construction, named end user, and capital on the record[D][T] †as of 2026-08-22Dispute this grade
A4Keystone ConnectTECfusions; former Alcoa siteWestmoreland3,000 (stated ambition)DEP review complete (air operating permit pending)initial phases exempt from the township moratorium; Phase 2 needs planning approvalyes — TensorWave (10 MW first tranche of a 1 GW commitment)$4.0B SPAC + $35M PIPE (7/2026); construction activeyesEstablishedRevised 2026-08-22 (was Partial): named end user and disclosed capital both surfaced in July 2026[D][T] †as of 2026-08-22Dispute this grade
A5Pennsylvania Digital I / PAX-1PA Data Center Partners + PowerHouse Data CentersCumberland1,350 (to 1.8 GW)Applied — pending; formerly Fast Trackcontested — zoning overlay under court challenge (filed 8/6/2026); Phase-1 final vote postponed to 9/2/2026, not yet takenno$15B JV announced; substation approvedyesPartial
re-review pending
Revised 2026-08-22 (was Established): the local-approvals leg is in litigation; the filing and capital legs hold[D][T] †as of 2026-08-22Dispute this grade
A6Project PhoenixAligned Data Centers; Frontier Group; Bruce Mansfield plant redevelopmentBeaver3,600 (site power)Applied — pending; formerly Fast Trackyes — borough conditional use approved 1/2026no (Aligned is the operator)$10B stated investment; $223M land closing 7/2026yesEstablishedApplication, local approval, capital, and an operator-owner on the record[D][T] †as of 2026-08-22Dispute this grade
A7Carbon Node East / Panther CreekKeel Infrastructure, formerly Bitfarms; T5Carbon350Applied — pending (DEP water-quality hearing held 8/20/2026)in progress, not in place — conditional preliminary approval only; county planning recommended conditional rejectionyes — Keel (self-use HPC)Macquarie $300M project financing; $100M drawnyesPartialRevised 2026-08-22 (was Established): drawn debt is real but the approvals leg was overstated[D][T] †as of 2026-08-22Dispute this grade
A8QTS SalemQTS / Blackstone, with PPLLuzernemulti-GW programApplied — pending; formerly Fast Trackyes — final master plan approved unanimously 7/9/2026; 1,700-acre consolidationyes — QTS (operator-owner)$25B QTS/Blackstone regional program; more than $500M in landyesEstablishedRevised 2026-08-22 (was Partial): the one missing leg, township approval, closed[D][T] †as of 2026-08-22Dispute this grade
A9Project HazelnutNorthPoint Development; Humboldt Industrial ParkLuzernenot publishedApplied — pending; formerly Fast Trackno — township rejected the land application 11/2025; appeal pending in Commonwealth CourtnoNorthPoint owns 1,500+ acres locallyyes, if revivedPartialLive DEP application against a local rejection; missing: local approval and either capital or an end user[D][T]as of 2026-08-22Dispute this grade
A10Project GravityArchbald 25 Developer LLCLackawannanot publishedApplied — pending; removed from Fast Track 5/2026partial — data-center overlay applies; overlay validity under appealnoland purchase agreements onlyyesPartialFiled, with overlay zoning; missing: capital and end user[D][T]as of 2026-08-22Dispute this grade
A11Kline Township DCAmazon Web ServicesSchuylkillnot publishedApplied — pending; formerly Fast Trackpartial — use permitted under a 2024 ordinance; land-development plan under township review (deadline extended to 9/30/2026)yes — AWS~350 acres purchased; AWS $20B PA programyesPartial
re-review pending
AWS money and a DEP application; local land-development approval unresolved[D][T] †as of 2026-08-22Dispute this grade
A12Project Boson / Highway Auto DCPDC Realty LLC / Kriger ConstructionLackawannanot publishedApplied — pendingpartial — zoning permit and subdivision filingsnonone disclosedyesPartialFilings are real; missing: capital and end user[D][T]as of 2026-08-22Dispute this grade
A13Project AtlasEdged US / CDC Acquisitions LLC; South Whitehall TownshipLehighnot publishedApplied — pendingpartial — industrial-zoned; township review ongoing, engineer could not recommend preliminary approval 7/2026nonone committed ($8.9B stated investment)yesPartial~1.5M sq ft planned (reduced from 5.1M); missing: capital and end user[D][T] †as of 2026-08-22Dispute this grade
A14Project ForgeSentinel Green Fig LLC; former Foote Mineral siteChesternot publishedApplied — pending (listed permits issued)yes — permitted use under township zoningnonone disclosed; PECO transmission security agreement covers the siteyesPartialApplication and zoning; missing: financing or end user[D][T] †as of 2026-08-22Dispute this grade
A15Highridge DCNorthPoint Development; end user NebiusSchuylkill1,200Applied — pending (NPDES issued; amendment pending)partial — zoned; Phase 3 rezoning tabled 8/18/2026, vote set for 8/31/2026yes — NebiusNebius bought ~358 acres for $187.5M; $13–15B stated investmentyesPartial
re-review pending
Named end user and application; approvals for the full build-out and committed capital unconfirmed[D][T] †as of 2026-08-22Dispute this grade
A16Wyalusing Energy Center DCKlondike Digital Infrastructure; New Fortress Energy siteBradford~248 (plant, per DEP plan approval)Applied — pending (air plan approval issued 10/2025)yes — zoned; sited with a planned off-grid gas plantnoNew Fortress land/power partnership; no data-center capital disclosedyesPartialApplication and site control; hinges on an unbuilt power plant and an unnamed tenant[D][T] †as of 2026-08-22Dispute this grade
A17Pitt Race Complex DCWampum I LLC / Provident Data Centers; operator SwitchBeavernot publishedApplied — pendingpartial — zoned; borough application filed 8/2026, under reviewyes — Switch (operator)$50M land purchaseyesPartialDEP application and named operator; municipal review only just begun[D][T] †as of 2026-08-22Dispute this grade
A18Springdale DCAllegheny DC Property Co.; former Cheswick plantAllegheny180Applied — pending (listed permits issued)yes — conditional use approved 5–2; six variances grantednonone disclosedyesPartialPermits and local approvals; missing: financing or end user[D][T]as of 2026-08-22Dispute this grade
A19Sharon DCKeel Infrastructure; former Westinghouse siteMercer110 (from 30 MW operating)Applied — pending; formerly Fast Trackyes — city council unanimous final land-development approvals 7/15/2026yes — Keel (self-use HPC)$5B project value; site operating today; 10/2026 construction startyesEstablishedRevised 2026-08-22 (was Partial): approvals essentially complete on an operating, self-funded site[D][T] †as of 2026-08-22Dispute this grade
A20Starpointe DCPrime Data Centers; Starpointe Business ParkWashington450 (behind-the-meter plant; reported, not filed)Applied — pending (major air plan approval submitted 4/2026)industrial zoning; conditional-use hearing contested, continued to 8/31/2026nonone disclosedyesPartial
re-review pending
Real permits and entitled land; missing: disclosed capital and tenant[D][T] †as of 2026-08-22Dispute this grade

† Row updated in the 2026-08-20 verification pass against DEP's permit-level data and named press. Table A: 7 Established · 13 Partial · 0 Announced only.

Table B — DEP-listed projects with no permit application (37)

A grade is not a forecast. It states which of three kinds of public evidence exist for this project on the date shown. Grades change when the record changes, and anyone can dispute one.

DEP Permits=NO rows: DEP lists them as "Proposed (No Applications Received)." None can be Established without a filing.

#ProjectCountyMWDEP stageLocal approvalsEnd userFinancing signalCOA-likelyGradeReasonSourcesAs of
B1Unnamed DCHomer City Redevelopment LLC; Kiewit, GE VernovaIndianacampus: 4,500 (power)Proposed — no data-center applications receivedyes — for the power campus; plant air permit issued 11/2025, construction since 4/2026no (data-center tenant unnamed)$10B+ campus; seven GE Vernova turbines orderedyesPartialThe energy campus is real; the data center has zero DEP filings and no named tenant (we grade the row, not the campus)[D][T]as of 2026-08-22Dispute this grade
B2Unnamed DCAmazon Web Services; Center TownshipIndiananot publishedProposed — no applications receivednot publishedyes — AWSAWS $20B PA programyesPartialAWS name on DEP's list at the Homer City location; nothing filed[D]as of 2026-08-22Dispute this grade
B3Project HummingbirdInternational Electric Power / Essential Utilities; former Robena MineGreene910Proposed — no applications received; formerly Fast Trackyes — zoned, land securednoEos storage partnership; 18 MGD water plant planned; no committed capital disclosedyesPartialCredible partners and a Fast Track history, but nothing filed with DEP[D][T]as of 2026-08-22Dispute this grade
B4Spring Mountain / Quakake TunnelNorthPoint DevelopmentCarbonnot publishedProposed — no applications receivedno — zoning not in placenoland purchasedno (nothing to file yet)Announced onlyLand bank and a press mention; no filings, no capital, no tenant[D][T]as of 2026-08-22Dispute this grade
B5Unnamed DCLinde Corporation; Clinton TownshipWaynenot publishedProposed — no applications receivedpartial — land-development application accepted 7/1/2026; decision due 9/28/2026; township moratorium contextnocompany-owned 743 acresyesPartialActive local land-development application on a clock[D][T]as of 2026-08-22Dispute this grade
B6Nescopeck / Valley View Wood DCLuzernenot publishedProposed — no applications receivednot publishednonone foundnot publishedAnnounced onlyNothing in the public record beyond the DEP row[D]as of 2026-08-22Dispute this grade
B7Unnamed DCs, “Project Scott”Archbald I LLC / Archbald II LLC / Provident RealtyLackawannanot publishedProposed — no applications receivedcontested — council denied 3/27/2026; developer claims deemed approval under the MPCnonone disclosedyes, if revivedPartialA deemed-approval claim could revive it; otherwise stalled[D][T]as of 2026-08-22Dispute this grade
B8Wildcat RidgePine Line Inc / Cornell Realty ManagementLackawanna1,600Proposed — no applications receivedno — overlay not adopted; residential/conservation zoning todayno~$2.1B announced, none committednoAnnounced only14-building paper campus; no zoning, no capital, no tenant[D][T]as of 2026-08-22Dispute this grade
B9Patrinely–Provident Real Estate DCArchbaldLackawannanot publishedProposed — no applications receivednot publishednonone foundnot publishedAnnounced onlyDEP row only; no public detail found[D]as of 2026-08-22Dispute this grade
B10Lower Mount Bethel Technology CenterPeron Development / J.G. PetrucciNorthampton1,200Proposed — no applications receivedno — agricultural zoning; rezone requiredno$5B announcednoAnnounced onlyAn announcement and the wrong zoning; nothing filed[D][T]as of 2026-08-22Dispute this grade
B11River Pointe DCUpper Mount Bethel TownshipNorthamptonnot publishedProposed — no applications receivednot publishednonone foundnot publishedAnnounced onlyNo public record found beyond the DEP row[D]as of 2026-08-22Dispute this grade
B12Project Gold / GouldsboroQuantm Group / 1778 Rich Pike LLC; NE EdgeLackawanna1,500Proposed — no applications receivedin litigation — zoning board denied; settlement vacated by the courtno300+ contiguous acres acquiredyes, if it prevailsPartialLand capital and active litigation keep it alive, barely[D][T]as of 2026-08-22Dispute this grade
B13Newport Ridge Data & Energy CenterLuzernenot publishedProposed — no applications receivednot publishednonone foundnot publishedAnnounced onlyDEP row only[D]as of 2026-08-22Dispute this grade
B14Project Green MountainGreen Mountain 6 LLC; former Stavola QuarryLackawannanot publishedProposed — no applications receivedpartial — land-development plans filed with the borough; overlay appliesnonone disclosedyesPartialReal local filings (seven buildings and a PPL switchyard); no capital or tenant[D][T]as of 2026-08-22Dispute this grade
B15Unnamed DCVerdantas / Prologis; 2500 Liberty Drive warehouse conversionNorthamptonnot publishedProposed — no applications receivedyes — unanimous township approval 3/2026no (tenant undisclosed)Prologis balance sheet; private substation plannedyesPartialApproved conversion by an investment-grade REIT; no DEP filings or tenant yet[D][T]as of 2026-08-22Dispute this grade
B16Unnamed DCLBT Investment Group LLC; Sugarloaf TownshipLuzernenot publishedProposed — no applications receivedno — township denied; litigation and ordinance disputenonone disclosednoAnnounced onlyA denial, no capital, no tenant[D][T]as of 2026-08-22Dispute this grade
B17Emaus Avenue warehouse conversionQuantm LLC; AllentownLehighnot publishedProposed — no applications receivedstalled — developer postponed review 6/2026nonone disclosednoAnnounced onlyThe developer itself paused it[D][T]as of 2026-08-22Dispute this grade
B18Unnamed DCBrewster Land Company; Dorrance TownshipLuzernenot publishedProposed — no applications receivedno — zoning-validity challenge only; no building application filednonone disclosednoAnnounced onlyA litigation posture without a project behind it[D][T]as of 2026-08-22Dispute this grade
B19Breaker Street DCBreaker Street Associates / Catalyst Commercial; JessupLackawanna600Proposed — no applications receivedunder appeal — zoning board rejected relief 1/2026; appealed 2/2026; grandfathered under pre-overlay rulesnonone disclosedyes, if revivedPartialA grandfathered application and a live appeal[D][T]as of 2026-08-22Dispute this grade
B20Sunnyside Road DCSunnyside Road Associates / Catalyst; JessupLackawannanot publishedProposed — no applications receivedyes — council approved preliminary plans 6/2026; construction slated 9/1/2026no$3.4M land (2024)yesPartialLocally approved and scheduled, but no DEP filings and no tenant[D][T]as of 2026-08-22Dispute this grade
B21Unnamed DCPocono Manor Investors; Tobyhanna TownshipMonroenot publishedProposed — no applications receivedoverlay adopted; no project filednonone disclosednoAnnounced onlyZoning groundwork only[D][T]as of 2026-08-22Dispute this grade
B22Smithfield GatewayDEPG Moiser Assoc. LPMonroenot publishedProposed — no applications receivedpartial — sketch plan (two data-center buildings, a hotel, restaurants)nonone disclosednoAnnounced onlyA mixed-use sketch plan; the data-center component is speculative[D][T]as of 2026-08-22Dispute this grade
B23West Hazleton DCOne Trinity Real EstateLuzernenot publishedProposed — no applications receivedno — zoning officer denied; site being marketednononenoAnnounced onlyA marketing exercise after a denial[D][T]as of 2026-08-22Dispute this grade
B24Scranton Materials DCRansom TownshipLackawannanot publishedProposed — no applications receivedno — zoning relief rejected 1/2026; two legal challenges filednonone disclosednoAnnounced onlyQuarry owner suing for zoning; no capital, no tenant[D][T]as of 2026-08-22Dispute this grade
B25Dickson City DCsDickson City Development LLC / KrigerLackawannanot publishedProposed — no applications receivedno — all four applications denied; challenge rejected 3–0 on 5/20/2026nonone disclosednoAnnounced onlyLocally dead absent new litigation[D][T]as of 2026-08-22Dispute this grade
B26TekPark expansionTierPoint; BreinigsvilleLehigh100Proposed — no applications receivedpartial — operating campus; expansion entitlements to be determinedyes — TierPoint (operator, existing customers)$240M securitization funded the acquisition and expansionyesPartialFunded operator expansion of an operating campus; no DEP filing yet[D][TP][DCD]as of 2026-08-22Dispute this grade
B27Unnamed DCKSR; Plains TownshipLuzernenot publishedProposed — no applications receivednot publishednonone foundnot publishedAnnounced onlyDEP row only[D]as of 2026-08-22Dispute this grade
B28Unnamed DCAvison Young; Wilkes-BarreLuzernenot publishedProposed — no applications receivednot publishednobroker listingnoAnnounced onlyA brokerage marketing a site[D]as of 2026-08-22Dispute this grade
B294-3 Salem Township DC4-3 Glen Brook GroupLuzerne3,500–4,000 (claimed)Proposed — no applications receivedno — zoning not in place; public hearing anticipatednoland assembly (~4,000 acres, 194 owners; ~$1.2B potential payout, uncommitted)noAnnounced onlyLand-option aggregation at an implausible scale; no filings, no committed capital[D][T]as of 2026-08-22Dispute this grade
B30Hunlock DCCastleton CommoditiesLuzernenot publishedProposed — no applications receivednot publishednoowner of the adjacent Hunlock Creek plantnot publishedAnnounced onlyPlausible siting next to an owned power plant; zero public project record[D]as of 2026-08-22Dispute this grade
B31Frackville DCKRNL Data Centers; New Castle TownshipSchuylkillnot publishedProposed — no applications receivedno — rezoning of conservation land merely floatednononenoAnnounced onlyA conversation with supervisors, not a project[D][T]as of 2026-08-22Dispute this grade
B32Unnamed DCHendricks; Penn Forest TownshipCarbonnot publishedProposed — no applications receivedno — township adopted a data-center ordinance; no application filedno~750 acres ownednoAnnounced onlyLandowner interest only[D][T]as of 2026-08-22Dispute this grade
B33Unnamed DCFezzik Energy / Five 9s Digital; Midland / AliquippaBeaver496 (marketed)Proposed — no applications receivedyes — site marketed as pre-approved behind-the-meter gasnosite marketing onlynoAnnounced onlyA listed site looking for a buyer[D][T]as of 2026-08-22Dispute this grade
B34Londonderry DCDauphinnot publishedProposed — no applications receivednot publishednonone foundnot publishedAnnounced onlyDEP row only; no public detail found[D]as of 2026-08-22Dispute this grade
B35Highlands East DCLower Swatara / Swatara Townships; likely Provident Realty — Dauphin Highlands assemblageDauphinnot publishedProposed — no applications receivedno — sale closes 12/31/2027; no development filingsno$45.6M golf-course purchase + ~$50M more parcels 3/2026yes, eventuallyPartial~$95M of land capital deployed; everything else missing[D][T]as of 2026-08-22Dispute this grade
B36Highlands West DCsame assemblage as B35Dauphinnot publishedProposed — no applications receivedno — as B35noas B35yes, eventuallyPartialAs B35: land capital deployed; everything else missing[D][T]as of 2026-08-22Dispute this grade
B37Zediker Station DCCNX, with JLLWashingtonnot published (site marketed)Proposed — no applications receivednot published — 1,500 acres marketednosite marketingnoAnnounced onlyGas company marketing acreage[D][T]as of 2026-08-22Dispute this grade

Table B: 0 Established · 13 Partial · 24 Announced only. B35 and B36 are one land assemblage that DEP lists as two projects.

Coverage and limits

What's in the full research

This page is the public reading. The working file behind it goes further, and we share it on request:

Individuals are not included in any research we share. Free on request; we ask who you are and what you need so we can send the right part.

Request the full research

or email research@datacenterpermits.org

Dispute a grade

Tell us the project, what you think the record shows instead, and where. We check the claim against the cited source and post the outcome on this page under Revisions.

Sources

Row-level facts marked † were checked on 2026-08-20 against the DEP permit-level CSV and named local and trade press (township notices, county and borough minutes, Times Leader, TribLive, WVIA, WESA, Fox56, Lehigh Valley Press, Sharon Herald, Beaver County Radio, Cumberlink, and company releases and SEC filings). Those citations are in the full research.